3,680 trips, ranked by where time was lost

One month of trip records from a cement producer’s limestone mines, broken down by shift, truck, cycle stage and operator.

MineralLimestone
RegionIndia
OperationOpen pit, two shifts
Starting stageStage 4: Integrated

The operation

Limestone mines supplying a cement producer.

A heavy earth-moving fleet on fixed routes between faces and crushers, run on two shifts.

One month of records: 3,680 trips and 3,38,400 tonnes moved.

The problem

Cycle times and output were reviewed as monthly averages, which hid where time was lost, on which shift and by which trucks.

How the work is phased

AnalyseEvery trip split into queue, load, haul, dump and return.
RankLosses ranked by the time and tonnes they cost.
ExtendFleet and fuel measurement for 200 machines across the company’s mines.

In detail

Second shift
Output shortfall traced to smaller trucks parked for the shift
Idle time
Idle recorded as empty haul, separated out
Large trucks
Running below their benchmark cycle
Cycle outliers
A long tail of slow cycles, isolated by route
Untagged material
Trips without a material tag, a royalty exposure
Operators
Cycle-time spread across operators on the same route

What changes on site

Today: Cycle time as a monthly average

Cycle split into queue, load, haul and dump

Today: Idle recorded as haul

Idle separated from empty haul

Today: Shift output compared in totals

Shortfall traced to fleet parked on one shift

Today: Untagged material

Material tagged per trip